Meeting the Challenges of Offshore Temporary Lighting & Power

Case Study: Mike Lafferty, E&I Maintenance Supervisor responsible for leading a team of electrical technician offshore

Water injection pump motor

On the Gryphon Alpha, the water injection pump had been redundant for a few months. When needed to be re-instated, the DC motor was damp. They considered sending the motor back to the beach which would...

Provide power supply to the Solan

Bi-Fab had the task of painting the legs for the Solan platform. They needed lighting and ventilation inside the tubes so EX power was needed. They had a shortage of power supply around the area so...

GDF SUEz E&P Nederland B.V. Spot repair in Potwatertank

GDF had a task to blast and paint the potwatertank. This involved steam cleaning the tank, get heat into the tank so it dried quickly then start blasting.

They had the heater running day and...

Replacing lagging on Vacuum Tower

PetroIneos had a very tight schedule to complete this task as HSE were stopping people from going in the tower until Temporary Lighting was fixed. Originally, they had planned to use fixed Lighting....